What Proposed in full means

A line counts as in full when Optiply originally proposed it and its final quantity exactly equals the original advised quantity. Increasing or decreasing that quantity makes the line fail this test. Restoring the original quantity makes it pass again.

The denominator includes all lines for which Optiply can determine a result. Lines marked as not originally proposed count in that denominator but score zero. Unknown results are excluded. Each eligible line has equal weight, regardless of units or purchase value.

How Optiply calculates Proposed in full

Proposed in full = matching proposed lines ÷ eligible lines × 100%.

Optiply groups the lines by supplier. It includes orders placed from one calendar month before the calculation date through that date. For a November 23 calculation, the window includes October 23 through November 23. This is a moving month, rather than the previous named month or a fixed 30-day period.

The supplier percentage uses the latest calculated result. It is not an average of daily percentages. No eligible lines produce a calculated result of zero.

Example: Proposed in full for four supplier order lines

Suppose one supplier has four eligible lines placed within the calculation's moving month. Proposed in full compares these lines with their original advice:

LineOriginally proposed?Original advised quantityFinal quantityCounts as in full?
AYes1010Yes
BYes2020Yes
CYes3025No
DNo—10No

Two lines match, so 2 ÷ 4 × 100% = 50%. If line C returns to 30 units, 3 ÷ 4 × 100% = 75%. The supplier's Proposed in full column shows 75% when its latest calculation includes that restored quantity.

Where to find Proposed in full in Optiply

The Suppliers list includes a Proposed in full column. The calculation rounds the fraction to three decimal places, equivalent to 0.1 percentage-point precision. The column then displays a whole percentage.

How Proposed in full differs from other supplier metrics

  • Proposed on time compares an order's actual placement date with its recorded planned order date. Exact same-date placement passes. It includes orders placed from one calendar month before the calculation date through that date. Its eligible lines can differ from those for Proposed in full.
  • % placed from advice counts orders linked to a planned ordering moment across the past 365 days. It compares order counts, rather than final line quantities.
  • Delivery in full compares delivered and ordered quantities for qualifying completed orders over three months. Quantities determine its weighting.
  • Delivery on time compares completion with the expected delivery date. Earlier completion can pass, unlike Proposed on time's exact-date test.

Keep these percentages separate. Multiplying separate on-time and in-full percentages does not calculate a joint OTIF result.